Keith 132 Greener Grid Park
- Connection date
- 1 Apr 2029 +46 months since 9 Dec
- Gate
- Gate 2
- Status
- Under Construction/Commissioning
- Technology
- Storage + Reactive compensation
- Total capacity
- 48 MW
- Connected now
- 0 MW
- Still to connect
- 48 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-001129
- In the register since
- November 2021
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 0 | 0 | 0 | None | Not stated | Built |
| 2 | 0 | 48 | 48 | 1 Apr 2029 | Gate 2 | Under Construction/Commissioning |
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 18 Sep 2026 registerStage 2: Status changed from Consents Approved to Under Construction/Commissioning
- 28 Jul 2026 registerConnection point changed from Keith 1 132/33kV GSP Substation to Keith 132kV Substation
- 28 Jul 2026 registerStage 2: Connection date moved from 31 May 2025 to 1 Apr 2029 (+46 months)
- 28 Jul 2026 registerStage 2: Given a Gate 2 connection offer
- 30 Sep 2025 registerStage 1: Technology changed from Storage to Storage, Reactive compensation
- 30 Sep 2025 registerStage 2: Technology changed from Storage to Storage, Reactive compensation
- 28 Mar 2025 registerStage 1: Technology changed from Storage, Reactive compensation to Storage
- 28 Mar 2025 registerStage 2: Technology changed from Storage, Reactive compensation to Storage
- 29 Oct 2024 registerStage 2: Connection date moved from 31 May 2024 to 31 May 2025 (+12 months)
- 28 Jul 2023 registerConnection point changed from Keith Compensation 132kV Substation to Keith 1 132/33kV GSP Substation
- 28 Jul 2023 registerStage 1: Technology changed from Reactive compensation to Storage, Reactive compensation
- 28 Jul 2023 registerStage 2: Technology changed from Reactive compensation to Storage, Reactive compensation
- 30 Jun 2023 registerRenamed from Keith 132 Sync. Compensation
- 30 Jun 2023 registerStage 2: 48 MW no longer connected
- 30 Jun 2023 registerStage 2: Capacity changed from 0 MW to 48 MW
- 30 Jun 2023 registerStage 2: Connection date set to 31 May 2024
- 30 May 2023 registerStage 2: 48 MW now connected
- 23 Dec 2022 registerSubstation name updated in the register (from Keith Compensation Substation 132kV to Keith Compensation 132kV Substation)
- 31 Dec 2021 registerNew stage added (48 MW from 31 Jan 2023)
- 30 Nov 2021 registerAdded to the register
Also at Keith 132kV Substation
Substation viewNo other projects in the register at this connection point.