Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / South Scotland
Connection date
31 Oct 2029
Gate
Not stated
Status
Awaiting Consents
Technology
Onshore wind
Total capacity
68 MW
Connected now
0 MW
Still to connect
68 MW
Transmission owner
SP Energy Networks (SPT)
Agreement type
Direct Connection
Region
South Scotland
Project number
PRO-001115
In the register since
January 2021 or earlier

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 18 Sep 2026 register
    Connection point changed from Margree 132kV Collector Substation to Margree 132/33kV Collector Substation
  • 30 May 2025 register
    Connection point changed from Troston Wind Farm 132kV Substation to Margree 132kV Collector Substation
  • 30 May 2025 register
    Connection date moved from 31 Oct 2027 to 31 Oct 2029 (+24 months)
  • 27 Feb 2024 register
    Customer changed from EDF ENERGY RENEWABLES LIMITED to TROSTON WINDFARM LIMITED
  • 28 Apr 2023 register
    Connection date moved from 31 Oct 2026 to 31 Oct 2027 (+12 months)
  • 23 Dec 2022 register
    Substation name updated in the register (from Troston Wind Farm 132kV to Troston Wind Farm 132kV Substation)
  • 29 Apr 2022 register
    Connection date moved from 30 Oct 2025 to 31 Oct 2026 (+12 months)

Also at Margree 132/33kV Collector Substation

Substation view

No other projects in the register at this connection point.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO