Airtnoch BESS
TURBINE MARKETING SPV LIMITED at Whitelee Extension 275/33kV
- Connection date
- Left 30 Sep 2025
- Gate
- Not stated
- Status
- Scoping
- Technology
- Solar
- Total capacity
- 89 MW
- Connected now
- 0 MW
- Still to connect
- 89 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-001107
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 146 registers from 29 Jan 2021 to 20 Oct 2026.
- 30 Sep 2025 registerLeft the register (89 MW from 29 Sep 2027)
- 24 Dec 2024 registerRenamed from Lochgoin Solar Farm
- 29 Oct 2024 registerConnection date moved from 1 Aug 2024 to 29 Sep 2027 (+38 months)
- 27 Sep 2024 registerSubstation name updated in the register (from Whitelee Extension to Whitelee Extension 275/33kV)
- 30 Jul 2021 registerConnection date moved from 25 Aug 2023 to 1 Aug 2024 (+11 months)
Also at Whitelee Extension 275/33kV
Substation view2 other projects, 121 MW still to connect at this substation in total.