Cleve Hill Solar Park
CLEVE HILL SOLAR PARK LIMITED at Cleve Hill 400kV Substation
- Connection date
- Increase at an existing station: +200 MW from 2 Jun 2036
- Gate
- Not stated
- Status
- Built
- Planning consent
- Granted 28 May 2020
Cleve Hill Solar Park (EN010085) · Source: Planning Inspectorate - Technology
- Demand + Storage + Solar
- Total capacity
- 550 MW
- Connected now
- 350 MW
- Still to connect
- 200 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001097
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Jul 2025 registerCapacity changed from 0 MW to 200 MW
- 29 Jul 2025 registerConnection date set to 2 Jun 2036
- 29 Jul 2025 registerTechnology changed from Storage, Solar to Demand, Storage, Solar
- 29 Apr 2025 register350 MW now connected
- 29 Apr 2025 registerStatus changed from Under Construction/Commissioning to Built
- 29 Sep 2023 registerConnection date moved from 31 Jul 2023 to 22 Mar 2024 (+8 months)
- 29 Sep 2023 registerStatus changed from Consents Approved to Under Construction/Commissioning
- 23 Dec 2022 registerSubstation name updated in the register (from Cleve Hill 400kV to Cleve Hill 400kV Substation)
- 29 Apr 2022 registerConnection date moved from 30 May 2022 to 31 Jul 2023 (+14 months)
Also at Cleve Hill 400kV Substation
Substation viewNo other projects in the register at this connection point.