- Connection date
- 1 Jul 2029
- Gate
- Not stated
- Status
- Consents Approved
- Technology
- Waste
- Total capacity
- 83 MW
- Connected now
- 0 MW
- Still to connect
- 83 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001096
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 18 Sep 2026 registerCustomer changed from EP SHB LIMITED to TTEP SHB LTD
- 28 Mar 2025 registerConnection date moved from 31 Jul 2026 to 1 Jul 2029 (+35 months)
- 29 Aug 2023 registerConnection date moved from 1 Jul 2025 to 31 Jul 2026 (+13 months)
- 23 Dec 2022 registerSubstation name updated in the register (from South Humber Bank 400kV to South Humber Bank 400kV Substation)
- 23 Dec 2022 registerConnection date moved from 10 Jan 2024 to 1 Jul 2025 (+18 months)
- 23 Dec 2022 registerStatus changed from Scoping to Consents Approved
- 23 Dec 2022 registerTechnology changed from Gas (CCGT) to Waste
- 30 Mar 2021 registerConnection date moved from 1 Jan 2023 to 10 Jan 2024 (+12 months)
Also at South Humber Bank 400kV Substation
Substation view1 other project, 118 MW still to connect at this substation in total.