Ayrshire Grid Services Facility
HUNTERSTON GRID 3 LTD at Ayrshire Grid 400kV Collector Substation
- Connection date
- 24 Mar 2028 (0 MW)
- Gate
- Gate 2
- Status
- Consents Approved
- Technology
- Reactive compensation
- Total capacity
- 0 MW
- Connected now
- 0 MW
- Still to connect
- 0 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-001090
- In the register since
- November 2021
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 16 Jun 2026 registerConnection date moved from 23 Mar 2028 to 24 Mar 2028 (1 day later)
- 12 Jun 2026 registerConnection date moved from 23 Mar 2026 to 23 Mar 2028 (+24 months)
- 12 Jun 2026 registerStatus changed from Scoping to Consents Approved
- 12 Jun 2026 registerGiven a Gate 2 connection offer
- 5 Jun 2026 registerConnection point changed from Hunterston East 400kV substation to Ayrshire Grid 400kV Collector Substation
- 24 Feb 2026 registerCustomer changed from FLEXIBLEGRIDPOWER LTD to HUNTERSTON GRID 3 LTD
- 29 Aug 2025 registerConnection date moved from 3 Sep 2025 to 23 Mar 2026 (+7 months)
- 29 Oct 2024 registerConnection date moved from 29 Mar 2024 to 3 Sep 2025 (+17 months)
- 28 Apr 2023 registerConnection date moved from 29 Apr 2024 to 29 Mar 2024 (−1 month)
- 30 Nov 2021 registerAdded to the register
Also at Ayrshire Grid 400kV Collector Substation
Substation viewNo other projects in the register at this connection point.