Monets Garden
- Connection date
- 8 Jun 2027 +31 months since 9 Dec
- Gate
- Gate 2
- Status
- Consents Approved
- Planning consent
- Granted 28 Mar 2025
York, reference 24/01851/FULM · Source: REPD - Technology
- Storage
- Total capacity
- 57 MW
- Connected now
- 0 MW
- Still to connect
- 57 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001082
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 14 Jul 2026 registerConnection date moved from 30 Oct 2024 to 8 Jun 2027 (+31 months)
- 10 Jul 2026 registerGiven a Gate 2 connection offer
- 23 Dec 2022 registerSubstation name updated in the register (from Osbaldwick 400kV to Osbaldwick 400kV Substation)
- 28 Jan 2022 registerCapacity changed from 49.9 MW to 57 MW
- 28 Jan 2022 registerConnection date moved from 30 Oct 2021 to 30 Oct 2024 (+36 months)
- 29 Oct 2021 registerRenamed from Osbaldwick
Also at Osbaldwick 400kV Substation
Substation view1 other project, 307 MW still to connect at this substation in total.