Wilton Lion BESS
SEMBCORP (WILTON BESS) LIMITED at Greystones A 275kV Substation
- Connection date
- Connected
- Gate
- Not stated
- Status
- Built
- Technology
- Storage
- Total capacity
- 150 MW
- Connected now
- 150 MW
- Still to connect
- 0 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001048
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 1 May 2026 registerCustomer changed from SEMBCORP UTILITIES (UK) LIMITED to SEMBCORP (WILTON BESS) LIMITED
- 10 Mar 2026 registerGate marking removed (was Gate 2)
- 24 Feb 2026 register150 MW now connected
- 24 Feb 2026 registerStatus changed from Under Construction/Commissioning to Built
- 24 Feb 2026 registerGiven a Gate 2 connection offer
- 30 Sep 2025 registerConnection date moved from 31 Oct 2035 to 13 Oct 2025 (−121 months)
- 29 Aug 2025 registerRestructured from 6 stages (150 MW from 30 Sep 2023, 210 MW from 30 Sep 2024, 340 MW from 11 Mar 2026, 490 MW from 30 Sep 2027, 275 MW from 30 Sep 2027, 235 MW from 30 Sep 2030) to 1 stage (150 MW from 31 Oct 2035). First connection date +145 months
- 28 Nov 2023 registerConnection point changed from Greystones GSP to Greystones A and B 275kV Substations
- 31 Oct 2023 registerStage 1: Technology changed from Gas (CCGT) to Storage, Gas (OCGT)
- 31 Oct 2023 registerStage 2: Technology changed from Gas (CCGT) to Storage, Gas (OCGT)
- 31 Oct 2023 registerStage 3: Technology changed from Gas (CCGT) to Storage, Gas (OCGT)
- 31 Oct 2023 registerStage 4: Technology changed from Gas (CCGT) to Storage, Gas (OCGT)
- 31 Oct 2023 registerStage 5: Technology changed from Gas (CCGT) to Storage, Gas (OCGT)
- 31 Oct 2023 registerStage 6: Technology changed from Gas (CCGT) to Storage, Gas (OCGT)
- 30 May 2023 registerStage 1: Status changed from Consents Approved to Under Construction/Commissioning
- 23 Dec 2022 registerSubstation name updated in the register (from Greystones to Greystones GSP)
- 28 Oct 2022 registerStage 1: Capacity changed from 340 MW to 150 MW
- 28 Oct 2022 registerStage 1: Connection date moved from 30 Sep 2024 to 30 Sep 2023 (−12 months)
- 28 Oct 2022 registerStage 2: Capacity changed from 850 MW to 210 MW
- 28 Oct 2022 registerStage 2: Connection date moved from 30 Sep 2026 to 30 Sep 2024 (−24 months)
- 28 Oct 2022 registerStage 3: Capacity changed from 275 MW to 340 MW
- 28 Oct 2022 registerStage 3: Connection date moved from 30 Sep 2027 to 11 Mar 2026 (−19 months)
- 28 Oct 2022 registerStage 4: Capacity changed from 235 MW to 490 MW
- 28 Oct 2022 registerStage 4: Connection date moved from 30 Sep 2030 to 30 Sep 2027 (−36 months)
- 28 Oct 2022 registerStage 4: Status changed from Awaiting Consents to Consents Approved
- 28 Oct 2022 registerNew stage added (275 MW from 30 Sep 2027)
- 28 Oct 2022 registerNew stage added (235 MW from 30 Sep 2030)
- 29 Jun 2021 registerStage 1: Capacity changed from 850 MW to 340 MW
- 29 Jun 2021 registerNew stage added (275 MW from 30 Sep 2027)
- 29 Jun 2021 registerNew stage added (235 MW from 30 Sep 2030)
Also at Greystones A 275kV Substation
Substation view1 other project, 700 MW still to connect at this substation in total.