Dell Wind Farm
- Connection date
- 1 Apr 2030
- Gate
- Not stated
- Status
- Consents Approved
- Planning consent
- Application submitted 11 Mar 2024
Scottish Government (S36), reference ECU00003440 · Source: REPD - Technology
- Onshore wind
- Total capacity
- 49.8 MW
- Connected now
- 0 MW
- Still to connect
- 49.8 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-001012
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 28 Mar 2025 registerConnection date moved from 31 Jul 2027 to 1 Apr 2030 (+32 months)
- 31 May 2024 registerConnection date moved from 30 Apr 2026 to 31 Jul 2027 (+15 months)
- 29 Jul 2022 registerSubstation name updated in the register (from Dell 132kv to Dell 132kV Substation)
- 29 Jul 2022 registerStatus changed from Awaiting Consents to Consents Approved
Also at Dell 132kV Substation
Substation viewNo other projects in the register at this connection point.