Druim Leathann BEGA
- Connection date
- 31 Mar 2027
- Gate
- Not stated
- Status
- Scoping
- Planning consent
- Granted 22 Jun 2022
Na h-Eileanan Siar, reference 18/00216/PPDM · Source: REPD - Technology
- Onshore wind
- Total capacity
- 49.7 MW
- Connected now
- 0 MW
- Still to connect
- 49.7 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Embedded
- Region
- North Scotland
- Project number
- PRO-000966
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Aug 2025 registerCustomer changed from BAYWA R.E. UK LIMITED to DRUIM LEATHANN WINDFARM LIMITED
- 29 Jul 2025 registerCustomer changed from DRUIM LEATHANN WINDFARM LIMITED to BAYWA R.E. UK LIMITED
- 30 Nov 2021 registerConnection point changed from Stornoway 132/33kV Substation to Stornoway GSP
- 30 Apr 2021 registerConnection date moved from 1 Apr 2025 to 31 Mar 2027 (+24 months)
- 26 Feb 2021 registerConnection date moved from 4 Jan 2025 to 1 Apr 2025 (+3 months)
Also at Stornoway GSP
Substation view1 other project, 74.7 MW still to connect at this substation in total.