Arbroath Battery Substation
- Connection date
- 21 Feb 2022
- Gate
- Not stated
- Status
- Consents Approved
- Planning consent
- Granted on appeal 20 Aug 2019
Angus, reference 18/00810/FULL · Source: REPD - Technology
- Storage
- Total capacity
- 35 MW
- Connected now
- 0 MW
- Still to connect
- 35 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Embedded
- Region
- North Scotland
- Project number
- PRO-000950
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 30 Nov 2021 registerSubstation name updated in the register (from Arbroath to Arbroath GSP)
- 28 Sep 2021 registerConnection date moved from 30 Sep 2021 to 21 Feb 2022 (+5 months)
- 30 Mar 2021 registerRenamed from Arbroath
Also at Arbroath GSP
Substation view2 other projects, 135 MW still to connect at this substation in total.