Transmission / Projects / South Scotland
Rigghill Windfarm
- Connection date
- Left 31 Oct 2023
- Gate
- Not stated
- Status
- Scoping
- Technology
- Onshore wind
- Total capacity
- 49.9 MW
- Connected now
- 0 MW
- Still to connect
- 49.9 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Embedded
- Region
- South Scotland
- Project number
- PRO-000941
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 146 registers from 29 Jan 2021 to 20 Oct 2026.
- 31 Oct 2023 registerLeft the register (49.9 MW from 30 Apr 2025)
- 23 Dec 2022 registerSubstation name updated in the register (from Spango Valley to Spango Valley GSP)
- 30 Apr 2021 registerConnection date moved from 30 Apr 2024 to 30 Apr 2025 (+12 months)
Also at Spango Valley GSP
Substation viewNo other projects in the register at this connection point.