Transmission / Projects / South Scotland

Rigghill Windfarm

RIGGHILL WIND FARM LIMITED at Spango Valley GSP

Connection date
Left 31 Oct 2023
Gate
Not stated
Status
Scoping
Technology
Onshore wind
Total capacity
49.9 MW
Connected now
0 MW
Still to connect
49.9 MW
Transmission owner
SP Energy Networks (SPT)
Agreement type
Embedded
Region
South Scotland
Project number
PRO-000941
In the register since
January 2021 or earlier

Change history

Every change to this project across 146 registers from 29 Jan 2021 to 20 Oct 2026.

  • 31 Oct 2023 register
    Left the register (49.9 MW from 30 Apr 2025)
  • 23 Dec 2022 register
    Substation name updated in the register (from Spango Valley to Spango Valley GSP)
  • 30 Apr 2021 register
    Connection date moved from 30 Apr 2024 to 30 Apr 2025 (+12 months)

Also at Spango Valley GSP

Substation view

No other projects in the register at this connection point.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO