Hare Craig Wind Farm
- Connection date
- 31 Oct 2028
- Gate
- Not stated
- Status
- Awaiting Consents
- Technology
- Onshore wind
- Total capacity
- 46.2 MW
- Connected now
- 0 MW
- Still to connect
- 46.2 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-000940
- In the register since
- November 2021
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Jul 2025 registerCustomer changed from ENERGYFARM UK HARE CRAIG LLP to HARE CRAIG WINDFARM LLP
- 26 Nov 2024 registerConnection date moved from 31 Oct 2027 to 31 Oct 2028 (+12 months)
- 30 Nov 2021 registerAdded to the register
Also at Hare Craig 33kV Substation
Substation viewNo other projects in the register at this connection point.