Tarland Battery Storage System
- Connection date
- 31 Oct 2026
- Gate
- Not stated
- Status
- Consents Approved
- Technology
- Storage
- Total capacity
- 20 MW
- Connected now
- 0 MW
- Still to connect
- 20 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Embedded
- Region
- North Scotland
- Project number
- PRO-000922
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 27 Oct 2026 registerConnection point changed from Tarland GSP to Tarland 132/33kV GSP Substation
- 30 Nov 2021 registerSubstation name updated in the register (from Tarland to Tarland GSP)
- 28 Sep 2021 registerConnection date moved from 4 Oct 2020 to 31 Oct 2026 (+73 months)
- 30 Mar 2021 registerRenamed from Tarland
- 26 Feb 2021 registerCustomer changed from CORONATION POWER LIMITED to Tarland Limited
- 26 Feb 2021 registerConnection date moved from 10 Apr 2020 to 4 Oct 2020 (+6 months)
Also at Tarland 132/33kV GSP Substation
Substation viewNo other projects in the register at this connection point.