Aikengall IIA Wind Farm
- Connection date
- Connected
- Gate
- Not stated
- Status
- Built
- Planning consent
- Granted on appeal 19 Oct 2016
Scottish Government (S36) · Source: REPD - Technology
- Onshore wind
- Total capacity
- 81.2 MW
- Connected now
- 81.2 MW
- Still to connect
- 0 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-000559
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Jul 2025 registerRenamed from AIKENGALL II WIND FARM
- 27 Sep 2024 registerRenamed from Middle Monynut BESS
- 30 Jul 2024 registerRenamed from Aikengall IIa Wind Farm
- 26 Mar 2024 registerCustomer changed from AIKENGALL IIA COMMUNITY WIND COMPANY LIMITED to AIK2A SUSTAINABLE ENERGY LTD
- 28 Nov 2023 registerSubstation name updated in the register (from Westerdod 132kV to Wester Dod 132kV)
- 28 Sep 2021 registerRestructured from 2 stages (5 MW from 2 Jul 2021, 76.2 MW connected) to 1 stage (81.2 MW connected)
- 26 Feb 2021 registerStage 2: Connection date moved from 7 Feb 2021 to 2 Jul 2021 (+5 months)
Also at Wester Dod 132kV
Substation view1 other project, 0 MW still to connect at this substation in total.