Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / North Scotland

Seagreen 1 Offshore Wind Farm

Seagreen Wind Energy Limited at Tealing 275/33kV Substation

Connection date
Connected
Gate
Not stated
Status
Built
Planning consent
Granted 16 May 2017
Marine Scotland · Source: REPD
Contract for Difference
Allocation Round 3
Technology
Offshore wind
Total capacity
1,075 MW
Connected now
1,075 MW
Still to connect
0 MW
Transmission owner
SSEN Transmission (SHET)
Agreement type
Direct Connection
Region
North Scotland
Project number
PRO-000527
In the register since
January 2021 or earlier

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 24 Dec 2024 register
    Restructured from 3 stages (10 MW from 15 Feb 2022, 590 MW from 1 Apr 2022, 475 MW from 1 Jul 2022) to 1 stage (1,075 MW connected)
  • 26 Nov 2024 register
    Stage 1: Status changed from Consents Approved to Built
  • 26 Nov 2024 register
    Stage 2: Status changed from Consents Approved to Built
  • 26 Nov 2024 register
    Stage 3: Status changed from Consents Approved to Built
  • 30 Jan 2024 register
    Customer changed from Berwick Bank B Limited to Seagreen Wind Energy Limited
  • 31 Mar 2023 register
    Customer changed from SEAGREEN WIND ENERGY LIMITED to Berwick Bank B Limited
  • 23 Dec 2022 register
    Substation name updated in the register (from Tealing 275/33kV to Tealing 275/33kV Substation)
  • 29 Jul 2022 register
    Renamed from Firth of Forth Phase 1
  • 29 Apr 2022 register
    Stage 1: Capacity changed from 270 MW to 10 MW
  • 29 Apr 2022 register
    Stage 1: Connection date moved from 31 Dec 2021 to 15 Feb 2022 (+2 months)
  • 29 Apr 2022 register
    Stage 2: Capacity changed from 330 MW to 590 MW
  • 30 Apr 2021 register
    Restructured from 1 stage (1,075 MW from 31 Dec 2021) to 3 stages (270 MW from 31 Dec 2021, 330 MW from 1 Apr 2022, 475 MW from 1 Jul 2022)

Also at Tealing 275/33kV Substation

Substation view

No other projects in the register at this connection point.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO

Planning consent

The planning decision or stage for this project, from DESNZ’s Renewable Energy Planning Database (REPD), July 2026 edition, with the planning authority and its reference. QueueWatch matched the project to that record. NESO’s status can lag behind planning decisions, so the two may differ.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.

Contract for Difference

The Contracts for Difference allocation round for this project, from DESNZ’s Renewable Energy Planning Database (REPD), July 2026 edition. QueueWatch matched the project to that record.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.