Whitegate Tertiary Connection
- Connection date
- Connected
- Gate
- Not stated
- Status
- Built
- Planning consent
- Granted 19 May 2022
Oldham, reference FUL/348501/22 · Source: REPD - Technology
- Storage
- Total capacity
- 57 MW
- Connected now
- 57 MW
- Still to connect
- 0 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000512
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 24 Sep 2026 register57 MW now connected
- 24 Sep 2026 registerStatus changed from Consents Approved to Built
- 28 Feb 2023 registerSubstation name updated in the register (from Whitegate GSP to Whitegate 275kV Substation)
- 28 Feb 2023 registerStatus changed from Scoping to Consents Approved
- 28 Feb 2023 registerTechnology changed from Gas engines to Storage
- 23 Dec 2022 registerSubstation name updated in the register (from Whitegate to Whitegate GSP)
- 28 Sep 2021 registerCapacity changed from 49.9 MW to 57 MW
- 28 Sep 2021 registerConnection date moved from 1 Oct 2022 to 30 Jun 2024 (+21 months)
- 26 Feb 2021 registerConnection date moved from 10 Jan 2022 to 1 Oct 2022 (+9 months)
Also at Whitegate 275kV Substation
Substation viewNo other projects in the register at this connection point.