Wylfa Substation
- Connection date
- 30 Jun 2029
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 120 MW
- Connected now
- 0 MW
- Still to connect
- 120 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000506
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 28 Feb 2025 registerCustomer changed from ENSO GREEN HOLDINGS LIMITED to WYLFA GREEN LIMITED
- 27 Sep 2024 registerConnection date moved from 31 Oct 2026 to 30 Jun 2029 (+32 months)
- 23 Dec 2022 registerSubstation name updated in the register (from Wylfa 132kV to Wylfa 132kV Substation)
- 30 Sep 2022 registerConnection date moved from 31 Oct 2024 to 31 Oct 2026 (+24 months)
Also at Wylfa 132kV Substation
Substation viewNo other projects in the register at this connection point.