Mill Hill Tertiary Connection
- Connection date
- 24 Oct 2025
- Gate
- Not stated
- Status
- Consents Approved
- Technology
- Storage
- Total capacity
- 57 MW
- Connected now
- 0 MW
- Still to connect
- 57 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000493
- In the register since
- September 2021
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 30 May 2025 registerConnection date moved from 30 Aug 2024 to 24 Oct 2025 (+14 months)
- 30 May 2023 registerStatus changed from Awaiting Consents to Consents Approved
- 28 Feb 2023 registerTechnology changed from Gas engines to Storage
- 23 Dec 2022 registerSubstation name updated in the register (from Mill Hill 275kV to Mill Hill 275kV Substation)
- 28 Sep 2021 registerAdded to the register
Also at Mill Hill 275kV Substation
Substation viewNo other projects in the register at this connection point.