QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / South Scotland

Knockodhar Wind Farm

REG KNOCKODHAR LIMITED at Knockodhar Wind Farm 132kV Substation

Connection date
30 Apr 2028
Gate
Not stated
Status
Scoping
Technology
Onshore wind
Total capacity
120 MW
Connected now
0 MW
Still to connect
120 MW
Transmission owner
SP Energy Networks (SPT)
Agreement type
Direct Connection
Region
South Scotland
Project number
PRO-000483
In the register since
January 2021 or earlier

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 27 Jun 2025 register
    Connection point changed from Mark Hill 275/132kV to Knockodhar Wind Farm 132kV Substation
  • 29 Oct 2024 register
    Connection point changed from Mark Hill 275/132/33kV to Mark Hill 275/132kV
  • 27 Sep 2024 register
    Connection point changed from Mark Hill 275kV Substation to Mark Hill 275/132/33kV
  • 28 Feb 2023 register
    Connection date moved from 30 Oct 2026 to 30 Apr 2028 (+18 months)
  • 23 Dec 2022 register
    Substation name updated in the register (from Mark Hill to Mark Hill 275kV Substation)

Also at Knockodhar Wind Farm 132kV Substation

Substation view

No other projects in the register at this connection point.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO