Rayleigh 2 Tertiary
ENSO GREEN HOLDINGS J LIMITED at Rayleigh Main 400kV Substation
- Connection date
- 31 Oct 2028
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 57 MW
- Connected now
- 0 MW
- Still to connect
- 57 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000466
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Jul 2025 registerCustomer changed from ENSO GREEN HOLDINGS LIMITED to ENSO GREEN HOLDINGS J LIMITED
- 27 Jun 2025 registerCapacity changed from 47.5 MW to 57 MW
- 24 Dec 2024 registerRestructured from 2 stages (49.9 MW from 31 Oct 2025, 7.1 MW from 31 Oct 2027) to 1 stage (47.5 MW from 31 Oct 2028). First connection date +36 months
- 28 Nov 2023 registerConnection point changed from Rayleigh Main GSP to Rayleigh Main 400kV Substation
- 23 Dec 2022 registerSubstation name updated in the register (from Rayleigh 'Main' to Rayleigh Main GSP)
Also at Rayleigh Main 400kV Substation
Substation view2 other projects, 144 MW still to connect at this substation in total.