Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / England and Wales

North Falls Offshore Wind Farm

NORTH FALLS OFFSHORE WIND FARM LIMITED at North Falls Offshore Platform Substation

Connection date
31 Oct 2030
Gate
Not stated
Status
Scoping
Planning consent
Granted 14 May 2026
The Planning Inspectorate - National Infrastructure, reference EN010119 · Source: REPD
Technology
Offshore wind
Total capacity
1,000 MW
Connected now
0 MW
Still to connect
1,000 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-000451
In the register since
January 2021 or earlier

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 30 Jan 2024 register
    Customer changed from SSE RENEWABLES SERVICES (UK) LIMITED to NORTH FALLS OFFSHORE WIND FARM LIMITED
  • 28 Apr 2023 register
    Transmission owner changed from OFTO to NGET
  • 23 Dec 2022 register
    Substation name updated in the register (from North Falls Offshore Platform to North Falls Offshore Platform Substation)
  • 29 Oct 2021 register
    Capacity changed from 500 MW to 1,000 MW

Also at North Falls Offshore Platform Substation

Substation view

No other projects in the register at this connection point.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO

Planning consent

The planning decision or stage for this project, from DESNZ’s Renewable Energy Planning Database (REPD), July 2026 edition, with the planning authority and its reference. QueueWatch matched the project to that record. NESO’s status can lag behind planning decisions, so the two may differ.