Priestgill Wind Farm
- Connection date
- 30 Nov 2026
- Gate
- Gate 2
- Status
- Consents Approved
- Planning consent
- Granted on appeal 7 Dec 2018
South Lanarkshire, reference CL/17/0009 · Source: REPD - Contract for Difference
- Allocation Round 6
- Technology
- Onshore wind
- Total capacity
- 43.6 MW
- Connected now
- 0 MW
- Still to connect
- 43.6 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-000448
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 19 Jun 2026 registerConnection point changed from Elvanfoot 400/275/33kV to Elvanfoot substation
- 19 Jun 2026 registerGiven a Gate 2 connection offer
- 28 Feb 2025 registerConnection point changed from Elvanfoot 275/132/33kV to Elvanfoot 400/275/33kV
- 28 Feb 2025 registerConnection date moved from 6 Dec 2024 to 30 Nov 2026 (+24 months)
- 30 Jun 2022 registerCapacity changed from 41 MW to 43.6 MW
- 30 Jun 2022 registerConnection date moved from 30 Nov 2022 to 6 Dec 2024 (+24 months)
- 28 May 2021 registerStatus changed from Awaiting Consents to Consents Approved
Also at Elvanfoot substation
Substation viewNo other projects in the register at this connection point.