Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / North Scotland
Connection date
30 Oct 2032
Gate
Not stated
Status
Consents Approved
Planning consent
Granted 2 Oct 2023
Scottish Government (S36), reference ECU00001844 · Source: REPD
Technology
Onshore wind
Total capacity
120 MW
Connected now
0 MW
Still to connect
120 MW
Transmission owner
SSEN Transmission (SHET)
Agreement type
Direct Connection
Region
North Scotland
Project number
PRO-000447
In the register since
January 2021 or earlier

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 30 May 2025 register
    Status changed from Awaiting Consents to Consents Approved
  • 29 Apr 2025 register
    Connection date moved from 30 Nov 2028 to 30 Oct 2032 (+47 months)
  • 27 Feb 2024 register
    Connection date moved from 1 Apr 2027 to 30 Nov 2028 (+20 months)
  • 23 Dec 2022 register
    Substation name updated in the register (from Energy Isles 132kV to Energy Isles 132kV Substation)
  • 30 Apr 2021 register
    Connection date moved from 1 Apr 2024 to 1 Apr 2027 (+36 months)
  • 26 Feb 2021 register
    Connection date moved from 4 Jan 2024 to 1 Apr 2024 (+3 months)
  • 26 Feb 2021 register
    Technology changed from Offshore wind to Onshore wind

Also at Energy Isles 132kV Substation

Substation view

No other projects in the register at this connection point.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO

Planning consent

The planning decision or stage for this project, from DESNZ’s Renewable Energy Planning Database (REPD), July 2026 edition, with the planning authority and its reference. QueueWatch matched the project to that record. NESO’s status can lag behind planning decisions, so the two may differ.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.