Energy Isles
ENERGY ISLES SHETLAND LIMITED at Energy Isles 132kV Substation
- Connection date
- 30 Oct 2032
- Gate
- Not stated
- Status
- Consents Approved
- Planning consent
- Granted 2 Oct 2023
Scottish Government (S36), reference ECU00001844 · Source: REPD - Technology
- Onshore wind
- Total capacity
- 120 MW
- Connected now
- 0 MW
- Still to connect
- 120 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-000447
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 30 May 2025 registerStatus changed from Awaiting Consents to Consents Approved
- 29 Apr 2025 registerConnection date moved from 30 Nov 2028 to 30 Oct 2032 (+47 months)
- 27 Feb 2024 registerConnection date moved from 1 Apr 2027 to 30 Nov 2028 (+20 months)
- 23 Dec 2022 registerSubstation name updated in the register (from Energy Isles 132kV to Energy Isles 132kV Substation)
- 30 Apr 2021 registerConnection date moved from 1 Apr 2024 to 1 Apr 2027 (+36 months)
- 26 Feb 2021 registerConnection date moved from 4 Jan 2024 to 1 Apr 2024 (+3 months)
- 26 Feb 2021 registerTechnology changed from Offshore wind to Onshore wind
Also at Energy Isles 132kV Substation
Substation viewNo other projects in the register at this connection point.