Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / North Scotland

Cloiche Wind Farm

SSE GENERATION LIMITED at Cloiche 132/33kV Substation

Connection date
1 Feb 2028
Gate
Not stated
Status
Scoping
Technology
Onshore wind
Total capacity
200 MW
Connected now
0 MW
Still to connect
200 MW
Transmission owner
SSEN Transmission (SHET)
Agreement type
Direct Connection
Region
North Scotland
Project number
PRO-000425
In the register since
January 2021 or earlier

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 1 Oct 2026 register
    Connection point changed from Cloich 132kV Substation to Cloiche 132/33kV Substation
  • 1 Oct 2026 register
    Transmission owner changed from SPT to SHET
  • 18 Sep 2026 register
    Transmission owner changed from SHET to SPT
  • 30 Sep 2025 register
    Connection date moved from 31 Jul 2027 to 1 Feb 2028 (+6 months)
  • 29 Jul 2025 register
    Connection point changed from Cloiche 132kV Substation to Cloich 132kV Substation
  • 26 Apr 2024 register
    Connection date moved from 31 Jul 2026 to 31 Jul 2027 (+12 months)
  • 23 Dec 2022 register
    Substation name updated in the register (from Cloiche 132kV to Cloiche 132kV Substation)
  • 29 Apr 2022 register
    Connection date moved from 1 Jul 2025 to 31 Jul 2026 (+13 months)
  • 26 Feb 2021 register
    Connection date moved from 7 Jan 2025 to 1 Jul 2025 (+6 months)

Also at Cloiche 132/33kV Substation

Substation view

No other projects in the register at this connection point.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO