High Constellation Windfarm
HIGH CONSTELLATION WINDFARM LIMITED at High Constellation 132/33kV Substation
- Connection date
- 31 Oct 2028 +15 months since 9 Dec
- Gate
- Gate 2
- Status
- Consents Approved
- Technology
- Onshore wind
- Total capacity
- 50 MW
- Connected now
- 0 MW
- Still to connect
- 50 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-000416
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 18 Sep 2026 registerStatus changed from Scoping to Consents Approved
- 28 Jul 2026 registerConnection date moved from 31 Jul 2027 to 31 Oct 2028 (+15 months)
- 28 Jul 2026 registerGiven a Gate 2 connection offer
- 30 Sep 2025 registerConnection point changed from Crossaig 132kV Substation to High Constellation 132/33kV Substation
- 31 Jan 2025 registerConnection date moved from 30 Apr 2025 to 31 Jul 2027 (+27 months)
- 23 Dec 2022 registerSubstation name updated in the register (from Crossaig 132kV to Crossaig 132kV Substation)
- 26 Feb 2021 registerConnection date moved from 31 Oct 2026 to 30 Apr 2025 (−18 months)
Also at High Constellation 132/33kV Substation
Substation viewNo other projects in the register at this connection point.