Transmission / Projects / England and Wales
Elstree (tertiary)
- Connection date
- Left 27 Jun 2025
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 57 MW
- Connected now
- 0 MW
- Still to connect
- 57 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000400
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 146 registers from 29 Jan 2021 to 20 Oct 2026.
- 27 Jun 2025 registerLeft the register (57 MW from 31 Oct 2030)
- 26 Nov 2024 registerRestructured from 2 stages (49.9 MW from 31 Oct 2025, 7.1 MW from 31 Oct 2027) to 1 stage (57 MW from 31 Oct 2030). First connection date +60 months
- 23 Dec 2022 registerSubstation name updated in the register (from Elstree 275kV to Elstree 275kV Substation)
Also at Elstree 275kV Substation
Substation viewNo other projects in the register at this connection point.