Bhlaraidh Extension Wind Farm
- Connection date
- 17 Aug 2029
- Gate
- Gate 1
- Status
- Scoping
- Planning consent
- Granted 30 Aug 2022
Scottish Government (S36), reference ECU00001900 · Source: REPD - Contract for Difference
- Allocation Round 5
- Technology
- Onshore wind
- Total capacity
- 101 MW
- Connected now
- 0 MW
- Still to connect
- 101 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-000383
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 27 Oct 2026 registerMarked as Gate 1
- 30 Sep 2025 registerConnection date moved from 1 Apr 2026 to 17 Aug 2029 (+41 months)
- 30 Apr 2021 registerConnection date moved from 31 Oct 2024 to 1 Apr 2026 (+17 months)
Also at Bhlaraidh 132/33kV Substation
Substation view1 other project, 101 MW still to connect at this substation in total.