Bridgwater (tertiary)
ENSO GREEN HOLDINGS H LIMITED at Bridgwater 400/132kV Substation
- Connection date
- 31 Aug 2028
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 57 MW
- Connected now
- 0 MW
- Still to connect
- 57 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000375
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 21 Nov 2025 registerConnection date moved from 1 Nov 2026 to 31 Aug 2028 (+22 months)
- 28 Mar 2025 registerConnection point changed from Bridgewater 400kV Substation to Bridgwater 400/132kV Substation
- 31 Jan 2025 registerCustomer changed from BRIDGWATER GREEN LIMITED to ENSO GREEN HOLDINGS H LIMITED
- 30 Jan 2024 registerConnection date moved from 31 Oct 2024 to 1 Nov 2026 (+24 months)
- 28 Jul 2023 registerSubstation name updated in the register (from Bridgwater 400kV Substation to Bridgewater 400kV Substation)
- 23 Dec 2022 registerSubstation name updated in the register (from Bridgwater 400kV to Bridgwater 400kV Substation)
Also at Bridgwater 400/132kV Substation
Substation view1 other project, 57 MW still to connect at this substation in total.