Aberarder Wind Farm
ABERARDER WIND FARM LLP at Aberarder Wind Farm 132/33kV Substation
- Connection date
- 31 Aug 2026
- Gate
- Not stated
- Status
- Consents Approved
- Planning consent
- Granted on appeal 7 Apr 2017
Highland, reference 15/00737/FUL · Source: REPD - Contract for Difference
- Allocation Round 5
- Technology
- Onshore wind
- Total capacity
- 50 MW
- Connected now
- 0 MW
- Still to connect
- 50 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-000368
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 26 Nov 2024 registerCapacity changed from 49.9 MW to 50 MW
- 26 Nov 2024 registerConnection date moved from 30 Aug 2025 to 31 Aug 2026 (+12 months)
- 29 Dec 2023 registerCapacity changed from 51.6 MW to 49.9 MW
- 29 Dec 2023 registerConnection date moved from 30 Aug 2024 to 30 Aug 2025 (+12 months)
Also at Aberarder Wind Farm 132/33kV Substation
Substation viewNo other projects in the register at this connection point.