Transmission / Projects / North Scotland

Sound of Islay Tidal

ISLAY TIDAL POWER LIMITED at Port Ann GSP

Connection date
Left 31 Oct 2023
Gate
Not stated
Status
Consents Approved
Technology
Tidal
Total capacity
10 MW
Connected now
0 MW
Still to connect
10 MW
Transmission owner
SSEN Transmission (SHET)
Agreement type
Embedded
Region
North Scotland
Project number
PRO-000355
In the register since
January 2021 or earlier

Change history

Every change to this project across 146 registers from 29 Jan 2021 to 20 Oct 2026.

  • 31 Oct 2023 register
    Left the register (10 MW from 30 Jun 2025)
  • 30 Nov 2021 register
    Substation name updated in the register (from Port Ann to Port Ann GSP)
  • 29 Oct 2021 register
    Connection date moved from 30 Nov 2021 to 30 Jun 2025 (+43 months)

Also at Port Ann GSP

Substation view

No other projects in the register at this connection point.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO