Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / South Scotland

Sanquhar II Wind Farm

SANQUHAR II COMMUNITY WIND CO LTD at Sanquhar II Wind Farm Substation

Connection date
17 Oct 2026 +3 months since 9 Dec
Gate
Gate 2
Status
Consents Approved
Technology
Onshore wind
Total capacity
250 MW
Connected now
0 MW
Still to connect
250 MW
Transmission owner
SP Energy Networks (SPT)
Agreement type
Direct Connection
Region
South Scotland
Project number
PRO-000352
In the register since
January 2021 or earlier

Stages

StageConnected MWAdds MWCumulative MWDateGateStatus
1013713717 Oct 2026Gate 2Consents Approved
2011325026 Nov 2027Gate 2Consents Approved

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 5 Nov 2026 register
    Stage 1: Connection date moved from 31 Jul 2026 to 17 Oct 2026 (+3 months)
  • 5 Nov 2026 register
    Stage 1: Given a Gate 2 connection offer
  • 5 Nov 2026 register
    Stage 2: Connection date moved from 28 Feb 2027 to 26 Nov 2027 (+9 months)
  • 5 Nov 2026 register
    Stage 2: Given a Gate 2 connection offer
  • 23 Dec 2025 register
    Connection point changed from Glenglass 132kV Substation to Sanquhar II Wind Farm Substation
  • 30 May 2025 register
    Restructured from 1 stage (250 MW from 30 Jul 2026) to 2 stages (137 MW from 31 Jul 2026, 113 MW from 28 Feb 2027)
  • 31 Jan 2025 register
    Connection date moved from 30 Apr 2024 to 30 Jul 2026 (+27 months)
  • 27 Sep 2024 register
    Substation name updated in the register (from Sanquhar 132/33kV Substation to Sanquhar 132/33kV)
  • 28 Jun 2024 register
    Customer changed from Sanquhar II Community Wind Company Limited to SANQUHAR II COMMUNITY WIND CO LTD
  • 29 Dec 2023 register
    Status changed from Scoping to Consents Approved
  • 23 Dec 2022 register
    Substation name updated in the register (from Sanquhar 132/33kV to Sanquhar 132/33kV Substation)

Also at Sanquhar II Wind Farm Substation

Substation view

No other projects in the register at this connection point.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO