Stornoway Wind Farm
- Connection date
- 31 Oct 2030
- Gate
- Not stated
- Status
- Consents Approved
- Technology
- Onshore wind
- Total capacity
- 180 MW
- Connected now
- 0 MW
- Still to connect
- 180 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-000346
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 19 Dec 2025 registerConnection point changed from Stornoway 132/33kV Substation to Arnish 275kV Substation
- 27 Feb 2024 registerConnection date moved from 31 May 2027 to 31 Oct 2030 (+41 months)
- 30 Mar 2022 registerConnection date moved from 1 Apr 2025 to 31 May 2027 (+26 months)
- 26 Feb 2021 registerConnection date moved from 4 Jan 2025 to 1 Apr 2025 (+3 months)
Also at Arnish 275kV Substation
Substation viewNo other projects in the register at this connection point.