Hornsea Power Station 2B
SOUNDMARK WIND LIMITED at Hornsea Platform 2B Offshore Substation
- Connection date
- Connected
- Gate
- Not stated
- Status
- Built
- Technology
- Offshore wind
- Total capacity
- 440 MW
- Connected now
- 440 MW
- Still to connect
- 0 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000334
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 28 Nov 2023 register440 MW now connected
- 23 Dec 2022 registerSubstation name updated in the register (from Hornsea Platform 2B Offshore to Hornsea Platform 2B Offshore Substation)
- 31 Aug 2021 registerStatus changed from Under Construction/Commissioning to Built
- 26 Feb 2021 registerConnection date moved from 8 Jan 2021 to 1 Aug 2021 (+7 months)
Also at Hornsea Platform 2B Offshore Substation
Substation viewNo other projects in the register at this connection point.