Scoop Hill Wind Farm
Community Windpower Limited at Scoop Hill Wind Farm 132kV Substation
- Connection date
- 31 Oct 2027
- Gate
- Gate 1
- Status
- Awaiting Consents
- Technology
- Onshore wind
- Total capacity
- 500 MW
- Connected now
- 0 MW
- Still to connect
- 500 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-000327
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 30 Oct 2026 registerMarked as Gate 1
- 18 Sep 2026 registerStatus changed from Scoping to Awaiting Consents
- 12 Dec 2025 registerCustomer changed from CWP Energy Limited to Community Windpower Limited
- 26 Nov 2024 registerConnection date moved from 28 Aug 2025 to 31 Oct 2027 (+26 months)
- 27 Sep 2024 registerCustomer changed from COMMUNITY WINDPOWER LIMITED to CWP Energy Limited
Also at Scoop Hill Wind Farm 132kV Substation
Substation viewNo other projects in the register at this connection point.