Pencloe Windfarm
- Connection date
- 1 Apr 2028
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Onshore wind
- Total capacity
- 115 MW
- Connected now
- 81 MW
- Still to connect
- 34 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-000323
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 81 | 0 | 81 | None | Gate 2 | Built |
| 2 | 0 | 34 | 115 | 1 Apr 2028 | Gate 1 | Scoping |
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 13 Oct 2026 registerStage 2: Status changed from Consents Approved to Scoping
- 18 Sep 2026 registerStage 2: Status changed from Awaiting Consents to Consents Approved
- 1 Sep 2026 registerStage 1: Technology changed from Storage, Onshore wind to Onshore wind
- 25 Aug 2026 registerStage 1: 81 MW now connected
- 25 Aug 2026 registerStage 1: Capacity changed from 85 MW to 81 MW
- 25 Aug 2026 registerStage 1: Status changed from Consents Approved to Built
- 25 Aug 2026 registerStage 1: Given a Gate 2 connection offer
- 25 Aug 2026 registerStage 2: Marked as Gate 1
- 31 Jan 2025 registerStage 1: Technology changed from Onshore wind to Storage, Onshore wind
- 31 Jan 2025 registerStage 2: Technology changed from Onshore wind to Storage, Onshore wind
- 28 Jun 2024 registerStage 1: Capacity changed from 81 MW to 85 MW
- 28 Jun 2024 registerStage 1: Connection date moved from 1 Jul 2024 to 1 Jul 2025 (+12 months)
- 28 Jun 2024 registerStage 2: Capacity changed from 38 MW to 34 MW
- 28 Jun 2024 registerStage 2: Connection date moved from 1 Apr 2026 to 1 Apr 2028 (+24 months)
- 28 Feb 2023 registerStage 1: Capacity changed from 79.8 MW to 81 MW
- 28 Feb 2023 registerStage 1: Connection date moved from 31 Jan 2024 to 1 Jul 2024 (+5 months)
- 28 Feb 2023 registerStage 2: Capacity changed from 16.2 MW to 38 MW
- 28 Feb 2023 registerStage 2: Connection date moved from 15 Aug 2025 to 1 Apr 2026 (+8 months)
- 23 Dec 2022 registerSubstation name updated in the register (from Pencloe 132/33kV to Pencloe 132/33kV Substation)
- 30 Aug 2022 registerStage 1: Connection date moved from 30 Jun 2023 to 31 Jan 2024 (+7 months)
- 30 Aug 2022 registerStage 2: Connection date moved from 29 Oct 2024 to 15 Aug 2025 (+10 months)
- 30 Apr 2021 registerStage 1: Connection date moved from 30 Jun 2022 to 30 Jun 2023 (+12 months)
Also at Pencloe 132/33kV Substation
Substation viewNo other projects in the register at this connection point.