Hopsrig Wind Farm
- Connection date
- 31 Oct 2027
- Gate
- Gate 2
- Status
- Consents Approved
- Technology
- Onshore wind
- Total capacity
- 48 MW
- Connected now
- 0 MW
- Still to connect
- 48 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-000318
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 3 Jul 2026 registerConnection point changed from Hopsrig Collector 132/33kV Substation to Hopsrig Collector Substation
- 3 Jul 2026 registerGiven a Gate 2 connection offer
- 29 Apr 2025 registerConnection date moved from 30 Nov 2026 to 31 Oct 2027 (+11 months)
Also at Hopsrig Collector Substation
Substation view1 other project, 84 MW still to connect at this substation in total.