Hesta Head Wind Farm

HESTA HEAD WIND FARM LIMITED at Hesta Head 132/33kV Substation

Connection date
Left 29 Apr 2025
Gate
Not stated
Status
Consents Approved
Technology
Onshore wind
Total capacity
20.4 MW
Connected now
0 MW
Still to connect
20.4 MW
Transmission owner
SSEN Transmission (SHET)
Agreement type
Direct Connection
Region
North Scotland
Project number
PRO-000308
In the register since
January 2021 or earlier

Change history

Every change to this project across 146 registers from 29 Jan 2021 to 20 Oct 2026.

  • 29 Apr 2025 register
    Left the register (20.4 MW from 30 Oct 2028)
  • 29 Dec 2023 register
    Connection date moved from 31 Mar 2027 to 30 Oct 2028 (+19 months)
  • 28 Jan 2022 register
    Connection date moved from 30 Apr 2025 to 31 Mar 2027 (+23 months)
  • 28 Jan 2022 register
    Status changed from Awaiting Consents to Consents Approved

Also at Hesta Head 132/33kV Substation

Substation view

No other projects in the register at this connection point.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.