Hesta Head Wind Farm
HESTA HEAD WIND FARM LIMITED at Hesta Head 132/33kV Substation
- Connection date
- Left 29 Apr 2025
- Gate
- Not stated
- Status
- Consents Approved
- Technology
- Onshore wind
- Total capacity
- 20.4 MW
- Connected now
- 0 MW
- Still to connect
- 20.4 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-000308
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 146 registers from 29 Jan 2021 to 20 Oct 2026.
- 29 Apr 2025 registerLeft the register (20.4 MW from 30 Oct 2028)
- 29 Dec 2023 registerConnection date moved from 31 Mar 2027 to 30 Oct 2028 (+19 months)
- 28 Jan 2022 registerConnection date moved from 30 Apr 2025 to 31 Mar 2027 (+23 months)
- 28 Jan 2022 registerStatus changed from Awaiting Consents to Consents Approved
Also at Hesta Head 132/33kV Substation
Substation viewNo other projects in the register at this connection point.