Glen Ullinish Wind Farm
GLEN ULLINISH WF LIMITED at Glen Ullinish 132/33kV Substation
- Connection date
- 16 Apr 2028 +18 months since 9 Dec
- Gate
- Not stated
- Status
- Consents Approved
- Planning consent
- Granted 24 Mar 2015
Highland, reference 14/03964/FUL · Source: REPD - Contract for Difference
- Allocation Round 7a
- Technology
- Onshore wind
- Total capacity
- 49.9 MW
- Connected now
- 0 MW
- Still to connect
- 49.9 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-000298
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 4 Sep 2026 registerConnection date moved from 31 Oct 2026 to 16 Apr 2028 (+18 months)
- 30 Aug 2022 registerConnection date moved from 31 Dec 2025 to 31 Oct 2026 (+10 months)
- 31 Dec 2021 registerCustomer changed from KILMAC ENERGY (GLEN ULLINISH) LTD to GLEN ULLINISH WF LIMITED
Also at Glen Ullinish 132/33kV Substation
Substation viewNo other projects in the register at this connection point.