Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / South Scotland

Caple Rig [formerly Faw Side Community Wind Farm]

Community Windpower Limited at Caple Rig 132kV Substation

Connection date
7 Sep 2029
Gate
Gate 1
Status
Scoping
Technology
Onshore wind
Total capacity
250 MW
Connected now
0 MW
Still to connect
250 MW
Transmission owner
SP Energy Networks (SPT)
Agreement type
Direct Connection
Region
South Scotland
Project number
PRO-000297
In the register since
January 2021 or earlier

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 27 Feb 2026 register
    Customer changed from CWP Energy Limited to Community Windpower Limited
  • 23 Dec 2025 register
    Marked as Gate 1
  • 30 Sep 2025 register
    Connection point changed from Faw Side Community Wind Farm Substation to Caple Rig 132kV Substation
  • 30 Sep 2025 register
    Status changed from Awaiting Consents to Scoping
  • 30 May 2025 register
    Renamed from Faw Side Community Wind Farm
  • 30 May 2025 register
    Connection date moved from 27 Apr 2028 to 7 Sep 2029 (+16 months)
  • 24 Dec 2024 register
    Connection date moved from 31 Oct 2025 to 27 Apr 2028 (+30 months)
  • 27 Sep 2024 register
    Customer changed from COMMUNITY WINDPOWER LIMITED to CWP Energy Limited
  • 23 Dec 2022 register
    Substation name updated in the register (from Faw Side Community Wind Farm to Faw Side Community Wind Farm Substation)

Also at Caple Rig 132kV Substation

Substation view

No other projects in the register at this connection point.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO