Tees Renewable Energy Plant
MGT TEESSIDE LIMITED at Teeside Connection Node A 132kV Substation
- Connection date
- Connected
- Gate
- Not stated
- Status
- Built
- Technology
- Biomass
- Total capacity
- 285 MW
- Connected now
- 285 MW
- Still to connect
- 0 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000278
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 30 Sep 2025 registerConnection point changed from Lackenby GSP to Teeside Connection Node A 132kV Substation
- 23 Dec 2022 registerSubstation name updated in the register (from Lackenby to Lackenby GSP)
Also at Teeside Connection Node A 132kV Substation
Substation view1 other project, 228 MW still to connect at this substation in total.