QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / South Scotland

Neart Na Gaoithe Offshore Wind Farm

NEART NA GAOITHE OFFSHORE WIND LIMITED at Neart Na Gaoithe 220/66KV Offshore Substation

Connection date
Connected
Gate
Not stated
Status
Built
Planning consent
Granted 16 May 2017
Marine Scotland · Source: REPD
Contract for Difference
Allocation Round 1
Technology
Offshore wind
Total capacity
448 MW
Connected now
448 MW
Still to connect
0 MW
Transmission owner
SP Energy Networks (SPT)
Agreement type
Direct Connection
Region
South Scotland
Project number
PRO-000273
In the register since
January 2021 or earlier

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 31 Oct 2025 register
    448 MW now connected
  • 31 Oct 2025 register
    Status changed from Consents Approved to Built
  • 23 Dec 2022 register
    Substation name updated in the register (from Neart Na Gaoithe 220/66KV Offshore to Neart Na Gaoithe 220/66KV Offshore Substation)
  • 31 May 2022 register
    Connection date moved from 1 Apr 2022 to 1 Jun 2023 (+14 months)
  • 30 Apr 2021 register
    Restructured from 2 stages (150 MW from 1 Oct 2021, 298 MW from 1 Apr 2022) to 1 stage (448 MW from 1 Apr 2022). First connection date +6 months
  • 26 Feb 2021 register
    Stage 1: Connection date moved from 10 Jan 2021 to 1 Oct 2021 (+9 months)
  • 26 Feb 2021 register
    Stage 2: Connection date moved from 4 Jan 2022 to 1 Apr 2022 (+3 months)

Also at Neart Na Gaoithe 220/66KV Offshore Substation

Substation view

No other projects in the register at this connection point.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO

Planning consent

The planning decision or stage for this project, from DESNZ’s Renewable Energy Planning Database (REPD), July 2026 edition, with the planning authority and its reference. QueueWatch matched the project to that record. NESO’s status can lag behind planning decisions, so the two may differ.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.

Contract for Difference

The Contracts for Difference allocation round for this project, from DESNZ’s Renewable Energy Planning Database (REPD), July 2026 edition. QueueWatch matched the project to that record.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.