Muaitheabhal Wind Farm
- Connection date
- 31 Dec 2030
- Gate
- Not stated
- Status
- Consents Approved
- Technology
- Pumped storage + Onshore wind
- Total capacity
- 189 MW
- Connected now
- 0 MW
- Still to connect
- 189 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-000272
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 27 Jun 2025 registerConnection date moved from 31 Oct 2030 to 31 Dec 2030 (+2 months)
- 27 Jun 2025 registerTechnology changed from Onshore wind to Pumped storage, Onshore wind
- 26 Mar 2024 registerCapacity changed from 150 MW to 189 MW
- 28 Feb 2023 registerConnection date moved from 31 Mar 2027 to 31 Oct 2030 (+43 months)
- 30 Apr 2021 registerConnection date moved from 1 Apr 2025 to 31 Mar 2027 (+24 months)
- 26 Feb 2021 registerConnection date moved from 4 Jan 2025 to 1 Apr 2025 (+3 months)
Also at Muaitheabhal 132/33kV Substation
Substation viewNo other projects in the register at this connection point.