QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / North Scotland

Muaitheabhal Wind Farm

UISENIS POWER LIMITED at Muaitheabhal 132/33kV Substation

Connection date
31 Dec 2030
Gate
Not stated
Status
Consents Approved
Technology
Pumped storage + Onshore wind
Total capacity
189 MW
Connected now
0 MW
Still to connect
189 MW
Transmission owner
SSEN Transmission (SHET)
Agreement type
Direct Connection
Region
North Scotland
Project number
PRO-000272
In the register since
January 2021 or earlier

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 27 Jun 2025 register
    Connection date moved from 31 Oct 2030 to 31 Dec 2030 (+2 months)
  • 27 Jun 2025 register
    Technology changed from Onshore wind to Pumped storage, Onshore wind
  • 26 Mar 2024 register
    Capacity changed from 150 MW to 189 MW
  • 28 Feb 2023 register
    Connection date moved from 31 Mar 2027 to 31 Oct 2030 (+43 months)
  • 30 Apr 2021 register
    Connection date moved from 1 Apr 2025 to 31 Mar 2027 (+24 months)
  • 26 Feb 2021 register
    Connection date moved from 4 Jan 2025 to 1 Apr 2025 (+3 months)

Also at Muaitheabhal 132/33kV Substation

Substation view

No other projects in the register at this connection point.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO