Projects / England and Wales
East Anglia One North
- Connection date
- 30 Oct 2029
- Gate
- Not stated
- Status
- Awaiting consent
- Technology
- Offshore wind
- Total capacity
- 880 MW
- Connected now
- 0 MW
- Still to connect
- 880 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000269
- Tracked since
- 14 Aug 2026
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 0 | 860 | 860 | 30 Oct 2029 | Not stated | Awaiting consent |
| 2 | 0 | 20 | 880 | 31 Oct 2034 | Not stated | Awaiting consent |
Change history
Every change to this project across 9 registers from 14 Aug 2026 to 21 Sep 2026.
No changes since 14 Aug 2026. Follow this project to see the next one on your watchlist.
Also queued at Friston 400kV Substation
Substation viewNo other projects in the register at this connection point.