Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / England and Wales

East Anglia One North

EAST ANGLIA ONE NORTH LIMITED at Friston 400kV Substation

Connection date
30 Oct 2029
Gate
Not stated
Status
Awaiting Consents
Planning consent
Granted 31 Mar 2022
East Anglia ONE North Offshore Windfarm (EN010077) · Source: Planning Inspectorate
Technology
Offshore wind
Total capacity
880 MW
Connected now
0 MW
Still to connect
880 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-000269
In the register since
January 2021 or earlier

Stages

StageConnected MWAdds MWCumulative MWDateGateStatus
1086086030 Oct 2029Not statedAwaiting Consents
202088031 Oct 2034Not statedAwaiting Consents

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 10 Mar 2026 register
    Customer changed from EAST ANGLIA ONE LIMITED to EAST ANGLIA ONE NORTH LIMITED
  • 16 Dec 2025 register
    Customer changed from EAST ANGLIA ONE NORTH LIMITED to EAST ANGLIA ONE LIMITED
  • 29 Aug 2025 register
    Customer changed from EAST ANGLIA ONE LIMITED to EAST ANGLIA ONE NORTH LIMITED
  • 29 Jul 2025 register
    Restructured from 1 stage (860 MW from 31 Mar 2028) to 2 stages (860 MW from 30 Oct 2029, 20 MW from 31 Oct 2034). First connection date +19 months
  • 27 Jun 2025 register
    Connection point changed from EA1N 275/66kV Offshore Platform to Friston 400kV Substation
  • 26 Apr 2024 register
    Connection date moved from 31 Mar 2026 to 31 Mar 2028 (+24 months)
  • 28 Apr 2023 register
    Transmission owner changed from OFTO to NGET
  • 28 Jan 2022 register
    Connection date moved from 30 Apr 2025 to 31 Mar 2026 (+11 months)
  • 28 May 2021 register
    Connection date moved from 1 Apr 2027 to 30 Apr 2025 (−23 months)
  • 26 Feb 2021 register
    Connection date moved from 4 Jan 2027 to 1 Apr 2027 (+3 months)

Also at Friston 400kV Substation

Substation view

No other projects in the register at this connection point.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO

Planning consent

The planning decision for this project, from the Planning Inspectorate. NESO’s status can lag behind planning decisions, so the two may differ.