Triton Knoll Offshore Wind Farm
TRITON KNOLL OFFSHORE WIND FARM LIMITED at Triton Knoll Offshore Substation
- Connection date
- Connected
- Gate
- Not stated
- Status
- Built
- Planning consent
- Granted 11 Jul 2013
Triton Knoll Offshore Wind Farm (EN010005) · Source: Planning Inspectorate - Contract for Difference
- Allocation Round 2
- Technology
- Offshore wind
- Total capacity
- 824 MW
- Connected now
- 824 MW
- Still to connect
- 0 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000193
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 23 Dec 2022 registerSubstation name updated in the register (from Triton Knoll Offshore to Triton Knoll Offshore Substation)
- 31 May 2022 register76 MW no longer connected
- 31 May 2022 registerCapacity changed from −76 MW to 0 MW
- 31 May 2022 registerConnection date removed (was 1 Apr 2022)
- 29 Jun 2021 registerRestructured from 2 stages (540 MW from 1 Apr 2021, 360 MW connected) to 1 stage (900 MW connected − 76 MW from 1 Apr 2022)
- 26 Feb 2021 registerStage 2: Connection date moved from 4 Jan 2021 to 1 Apr 2021 (+3 months)
Also at Triton Knoll Offshore Substation
Substation viewNo other projects in the register at this connection point.