Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / England and Wales

Triton Knoll Offshore Wind Farm

TRITON KNOLL OFFSHORE WIND FARM LIMITED at Triton Knoll Offshore Substation

Connection date
Connected
Gate
Not stated
Status
Built
Planning consent
Granted 11 Jul 2013
Triton Knoll Offshore Wind Farm (EN010005) · Source: Planning Inspectorate
Contract for Difference
Allocation Round 2
Technology
Offshore wind
Total capacity
824 MW
Connected now
824 MW
Still to connect
0 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-000193
In the register since
January 2021 or earlier

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 23 Dec 2022 register
    Substation name updated in the register (from Triton Knoll Offshore to Triton Knoll Offshore Substation)
  • 31 May 2022 register
    76 MW no longer connected
  • 31 May 2022 register
    Capacity changed from −76 MW to 0 MW
  • 31 May 2022 register
    Connection date removed (was 1 Apr 2022)
  • 29 Jun 2021 register
    Restructured from 2 stages (540 MW from 1 Apr 2021, 360 MW connected) to 1 stage (900 MW connected − 76 MW from 1 Apr 2022)
  • 26 Feb 2021 register
    Stage 2: Connection date moved from 4 Jan 2021 to 1 Apr 2021 (+3 months)

Also at Triton Knoll Offshore Substation

Substation view

No other projects in the register at this connection point.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO

Planning consent

The planning decision for this project, from the Planning Inspectorate. NESO’s status can lag behind planning decisions, so the two may differ.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.

Contract for Difference

The Contracts for Difference allocation round for this project, from DESNZ’s Renewable Energy Planning Database (REPD), July 2026 edition. QueueWatch matched the project to that record.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.