Lochay (Part of Killin Cascade Hydro Scheme)
- Connection date
- 1 Jan 2027
- Gate
- Not stated
- Status
- Under Construction/Commissioning
- Technology
- Hydro
- Total capacity
- 51.2 MW
- Connected now
- 45 MW
- Still to connect
- 6.2 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-000174
- In the register since
- January 2021 or earlier
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 45 | 0 | 45 | None | Not stated | Built |
| 2 | 0 | 6.2 | 51.2 | 1 Jan 2027 | Not stated | Under Construction/Commissioning |
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 1 Oct 2026 registerConnection point changed from Lochay GSP to Lochay 132/11kV Substation
- 26 Nov 2024 register2 MW no longer connected
- 26 Nov 2024 registerNew stage added (6.2 MW from 1 Jan 2027)
- 23 Dec 2022 registerSubstation name updated in the register (from Lochay to Lochay GSP)
Also at Lochay 132/11kV Substation
Substation viewNo other projects in the register at this connection point.