Elchies Wind Farm
- Connection date
- 30 Nov 2028
- Gate
- Not stated
- Status
- Scoping
- Technology
- Onshore wind
- Total capacity
- 170 MW
- Connected now
- 0 MW
- Still to connect
- 170 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-000151
- In the register since
- January 2021 or earlier
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 0 | 99 | 99 | 30 Nov 2028 | Not stated | Scoping |
| 2 | 0 | 71 | 170 | 30 Nov 2028 | Not stated | Scoping |
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Oct 2024 registerStage 1: Connection date moved from 30 Jun 2027 to 30 Nov 2028 (+17 months)
- 29 Oct 2024 registerStage 2: Connection date moved from 30 Jun 2028 to 30 Nov 2028 (+5 months)
- 27 Feb 2024 registerNew stage added (71 MW from 30 Jun 2028)
- 30 Mar 2022 registerConnection date moved from 30 Jun 2025 to 30 Jun 2027 (+24 months)
Also at Elchies 132/33kV Substation
Substation viewNo other projects in the register at this connection point.