Douglas West
- Connection date
- Connected
- Gate
- Not stated
- Status
- Built
- Technology
- Onshore wind
- Total capacity
- 45 MW
- Connected now
- 45 MW
- Still to connect
- 0 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-000128
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 27 Sep 2024 registerConnection point changed from Coalburn 132/33kV Substation to Coalburn 400/132kV
- 23 Dec 2022 registerSubstation name updated in the register (from Coalburn 132/33kV to Coalburn 132/33kV Substation)
- 30 Jul 2021 register45 MW now connected
- 30 Jul 2021 registerStatus changed from Under Construction/Commissioning to Built
Also at Coalburn 400/132kV
Substation view1 other project, 0 MW still to connect at this substation in total.