Stranoch Wind Farm
STRANOCH WINDFARM LIMITED at Stranoch Wind 132/33kV Substation
- Connection date
- 18 Dec 2026 +2 months since 9 Dec
- Gate
- Gate 2
- Status
- Under Construction/Commissioning
- Technology
- Onshore wind
- Total capacity
- 102 MW
- Connected now
- 0 MW
- Still to connect
- 102 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-000127
- In the register since
- January 2021 or earlier
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 0 | 82 | 82 | 18 Dec 2026 | Gate 2 | Under Construction/Commissioning |
| 2 | 0 | 20 | 102 | 30 Apr 2027 | Gate 2 | Under Construction/Commissioning |
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 30 Oct 2026 registerRestructured from 1 stage (102 MW from 18 Dec 2026) to 2 stages (82 MW from 18 Dec 2026, 20 MW from 30 Apr 2027)
- 18 Sep 2026 registerStatus changed from Consents Approved to Under Construction/Commissioning
- 25 Aug 2026 registerConnection date moved from 9 Oct 2026 to 18 Dec 2026 (+2 months)
- 25 Aug 2026 registerGiven a Gate 2 connection offer
- 24 Dec 2024 registerConnection date moved from 29 Aug 2025 to 9 Oct 2026 (+13 months)
- 30 Jul 2024 registerCustomer changed from EDF ENERGY RENEWABLES LIMITED to Stranoch Windfarm Limited
- 29 Aug 2023 registerConnection date moved from 30 Sep 2024 to 29 Aug 2025 (+11 months)
- 23 Dec 2022 registerSubstation name updated in the register (from Stranoch Wind 132/33KV to Stranoch Wind 132/33KV Substation)
Also at Stranoch Wind 132/33kV Substation
Substation viewNo other projects in the register at this connection point.