Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / South Scotland

Andershaw Wind Farm

ANDERSHAW WIND POWER LIMITED at Linnmill 132/33kV

Connection date
Connected
Gate
Not stated
Status
Built
Planning consent
Granted 9 Jun 2014
South Lanarkshire, reference CL/07/0454 · Source: REPD
Technology
Onshore wind
Total capacity
35 MW
Connected now
35 MW
Still to connect
0 MW
Transmission owner
SP Energy Networks (SPT)
Agreement type
Embedded
Region
South Scotland
Project number
PRO-000010
In the register since
January 2021 or earlier

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 29 Oct 2024 register
    Connection point changed from Linmill 132/33kV to Linnmill 132/33kV
  • 27 Sep 2024 register
    Substation name updated in the register (from Linmill 132/33kV Substation to Linmill 132/33kV)
  • 28 Nov 2023 register
    Connection point changed from Linnmill 132/33kV to Linmill 132/33kV Substation

Also at Linnmill 132/33kV

Substation view

1 other project, 0 MW still to connect at this substation in total.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO

Planning consent

The planning decision or stage for this project, from DESNZ’s Renewable Energy Planning Database (REPD), July 2026 edition, with the planning authority and its reference. QueueWatch matched the project to that record. NESO’s status can lag behind planning decisions, so the two may differ.